欢迎来到思摩特项目管理官方网站! 南京 | 镇江 | 扬州 | 常州 | 芜湖 | 马鞍山 | 滁州 等地区指定项目管理培训中心

加入收藏

    联系我们
  • 全国24小时免费咨询电话:
    400-805-8908

    welcome@smartpm.com.cn

    • 郑州PMP网课|在线模拟题

  • 发布时间:2020-01-10 16:47:17  来源:思摩特 www.smartpm.com.cn  浏览量:0
  • 编辑导读:本文为大家介绍的是郑州PMP网课|在线模拟题,下面是郑州PMP网课班的具体内容,供大家参考,更多PMP考试相关资讯可关注思摩特项目管理

    本文为大家介绍的是郑州PMP网课|在线模拟题,下面是郑州PMP网课班的具体内容,供大家参考,更多PMP考试相关资讯可关注思摩特项目管理

    思摩特PMP办学资质

    ↑ PMI授权办学资质(11年~12年)↑最新资质在PMI官方网站或者思摩特百度百科查询(十余年PMP、ACP等项目管理教学保证

     

    01、The project manager conducts an interview with a key stakeholder. This stakeholder insist that the project be completed by a certain date to allow the resulting product to be ready for manufacture in time for a critical trade 

     

    exhibition. The stakeholder also insists that the product pass existing international safety standards. The stakeholder will not release the funds need for the project kick-off unless both conditions are included.

     

    Where must the project manager include these conditions?

     

    A. Project summary milestones

     

    B. Project high-level requirements

     

    C. Project contract summary

     

    D. Project exit criteria

     

    项目经理会见了一个主要利害关系者。该利害关系者坚持认为,应在某日期完成项目,以便及时安排产品生产并参加某个贸易展览会。利害关系者还认为产品必须达到现行国际安全标准。只有接受这两个条件,利害关系者才能提供项目所

     

    需启动资金。项目经理应将这些条件纳入下列哪一项?

     

    A、项目主要里程碑

     

    B、项目概括性需求

     

    C、项目合同摘要

     

    D、项目退出标准

    郑州PMP网课班在线模拟题1

    02、A product developed in a project is now being tested by the customer for acceptance. The customer complains that the product delivered does not meet their acceptance criteria. The project manager reviews the customer

     

    acceptance test plan and realizes that their acceptance plan includes features that were not in the agreed requirements.

     

    What should the project manager do next?

     

    A. Review and update the requirements to include the additional features

     

    B. Assign the project team to develop the additional features so that customer acceptance can be achieved

     

    C. Tell the customer that the feature are additional and initiate change control

     

    D. Tell the customer that they must change their acceptance plan to remove the additional features

     

    某项目开发的产品正处于客户验收测试阶段。客户抱怨交付的产品未能满足其验收标准。项目经理审查了客户验收测试计划并发现其验收计划含有约定需求之外的功能。

     

    项目经理接下来应该怎么做?

     

    A、评审并更新需求,使之包括额外功能

     

    B、指派项目团队开发额外功能,以确保通过客户验收

     

    C、告知客户这些属于额外功能并启动变更控制

     

    D、告知客户,他们必须更改验收计划删除额外功能

    郑州PMP网课班在线模拟题2

     

    03、During the project execution, a change request is submitted, analyzed, approved, and reflected the project plans. Later, during validating scope process, a deliverable is found complete according to the original plans, but prior to the

     

    change request implementation.

     

    Which action could have prevented this from happening?

     

    A. Effective stakeholder identification

     

    B. Involvement of stakeholders in the change request approval process

     

    C. Effective communication of change requests

     

    D. Increased investments on scope control

     

    在项目执行期间提交、分析和批准了一项变更请求,并在项目计划中加以反映。之后在确认范围过程中,发现可交付成果仅在变更请求实施前完全符合原计划。

     

    哪种行为可防止发生这种情况?

     

    A、有效的利害关系者识别

     

    B、让利害关系者参与变更批准过程

     

    C、有效沟通变更请求

     

    D、增加对范围控制的投入

    郑州PMP网课班在线模拟题3

    热门推荐

    分享到 更多
  • PMI®, PMP®, PMI-ACP® and PMBOK® are registered marks of the Project Management Institute, Inc.

    电话:025-84547600 / 13390908908 / 400-805-8908 / 传真:025-84547600 / 邮箱:welcome@smartpm.com.cn / Weixin:13327831928

    Copyright © 2009-2024 南京思摩特企业管理咨询有限公司 版权所有  苏ICP备11012816号-2   苏公网安备 32011402010832号

    技术支持:软月互动  

  • 咨询反馈
    扫码关注

    PMP、ACP项目管理培训顾问

    思摩特公众号

    返回顶部