欢迎大家来到思摩特新疆PMP培训班,今天总结了我们部分学员的一些易错PMP考试试题给大家分享下:
1. A control chart should always contain:
A. Upper and lower warning limits
B. The moving average
C. Upper and lower control limits
D. Upper and lower specification limits
1. 控制图应该包含:
A. 上下告警界限
B. 一定平均值
C. 上下控制界限
D. 上下规格界限
2. When is Rolling Wave Planning useful in a project?
A. You should use Rolling Wave Planning to help you achieve the appropriate level of detail in each work package at the right time.
B. You should use Rolling Wave Planning to determine the correct sequencing for long-term items.
C. You should use Rolling Wave Planning to help you organize team members’ activities within a large project group.
D. You should use Rolling Wave Planning to help you determine which activities are more important and to do them first
2. 在项目中滚动式规划什么时候有用?
A. 你应该使用滚动式规划来帮助你在适当的时机实现每个工作包合适的细节级别。
B. 你应该使用滚动式规划来确定长期事项的正确排序。
C. 你应该使用滚动式规划来帮助你在大型项目组中组织团队成员的活动。
D. 你应该使用滚动式规划来帮助你确定哪些活动更重要,并且首先去实施这些活动。
3. A good project manager always gathers and documents lessons learned throughout the project lifecycle rather than delaying the effort until the project closure. Which of the following is not a risk associated with postponing the lessons-learned gathering effort until the very end of the project?
A. The project manager has fewer resources available.
B. The project’s earned value decreases.
C. Not all lessons learned might get captured.
D. The effort might seem boring and non-value-adding.
3. 一个好的项目经理总是在整个项目期间收集经验教训,而不是到项目收尾时才做。以下哪一项不是与项目快要收尾时才进行经验教训收集相关联的风险?
A. 项目经理只有较少的可用资源
B. 项目的挣值下降
C. 可能不会收集到所有经验教训
D. 这种工作看起来无聊并且没有增加值