1. Thinking back to lessons that your company learned from experiences with its legacy information systems during the Y2K dilemma, you finally convinced management to consider systems maintenance from the beginning of the project. However, maintenance should—
a. Always be included as an activity to be performed during the closeout phase
b. Have a separate phase in the life cycle for information systems project because 60% to 70% of computer systems’ life-cycle costs generally are devoted to maintenance
c. Not be viewed as part of the project life cycle
d. Be viewed as a separate project
回想“千年虫”困境给遗产信息系统带来的经验教训,你最终说服管理层从项目伊始就考虑系统日常维护,但是,维护应该__
A.总是被作为收尾阶段中实施的一个活动
B.在信息系统项目生命周期设一个独立的阶段,因为电脑系统生命周期成本的60%-70%用于系统维护
C.不被看做项目生命周期的一部分
D.被看做一个独立的项目
2. On your systems development project, you noted during a review that the system had less functionality than planned at the critical design review. This note suggests that during the control risks process you used which following tools and techniques?
a. Risk reassessment
b. Variance analysis
c. Technical performance analysis
d. Reserve analysis
在系统开发项目上,你在评审中发现系统比当初在关键设计方案评审时规划的功能要少,并记录了下来。在记录中建议使用以下哪种监督风险过程的工具?
A.风险再评估
B.偏差分析
C.技术绩效分析
D.储备分析
3. 以下都是导致项目复杂性的维度,除了?
A.系统行为
B.人类行为
C.模糊性或不确定性
D.渐进明细