    1、A new team member with no practical projectexperience is assigned to an ongoing project. The project manager assigns adifficult task to the new team member.What action should the project managernow take?

     

    A. Assign a mentor for the new team memberand closely monitor their progress

     

    B. Recommend that the new member undertakea self-study training program

     

    C. Allow the new team member to work alone,but report daily to the project manager.

     

    D. Provide the new team member with theproject management plan and assign a contact person.

     

    一名没有实际项目经验的新团队成员被分配到一个正在进行当中的项目。项目经理向该团队成员分配了一项困难任务。项目经理现在应该采取什么措施?

     

    A.为该新团队成员分配一位指导者,并密切监测他们的进展情况。

     

    B.建议该新团队成员参加自学培训课程。

     

    C.允许该新团队成员单独工作,但应每日向项目经理报告工作。

     

    D.向该新团队成员提供项目管理计划,并指定—名联系人。

    西安PMP在线模拟题1

    2、In a weekly meeting, a project team members report that they are unaware of what task is to be performed next, what should the project manager review with the team member?

     

    A.Work breakdown structure (WBS)

     

    B.Project schedule

     

    C.Critical path

     

    D.Milestone list

     

    在一次周会上,项目团队成员报告他们不知道下一步要执行什么任务。项目经理应与团队成员查阅下列哪一项?

    A.工作分解结构(WBS)

     

    B.项目进度计划

     

    C.关键路径

     

    D.里程碑清单 

    西安PMP在线模拟题2

    3、During a time-critical project, various workflows are operating in parallel. Which of the following quality control measures should the project manager apply to indicate when a schedule for one of the workflows is above the upper specification limits?

     

    A.Tolerance limits

     

    B.Control limits

     

    C.Variable sampling

     

    D.Attribute sampling

     

    在一个对时间要求严格的项目中,不同工作流并行操作。项目经理应应用下列哪一项质量控制措施来表示其中一个工作流的进度高于规格上限?

     

    A.公差界限

     

    B.控制界限

     

    C.变量抽样

     

    D.属性抽样

    西安PMP在线模拟题3

     

    热门推荐

    分享到 更多
  • PMI®, PMP®, PMI-ACP® and PMBOK® are registered marks of the Project Management Institute, Inc.

    电话:025-84547600 / 13390908908 / 400-805-8908 / 传真:025-84547600 / 邮箱:welcome@smartpm.com.cn / Weixin:13327831928

    Copyright © 2009-2024 南京思摩特企业管理咨询有限公司 版权所有  苏ICP备11012816号-2   苏公网安备 32011402010832号

    技术支持:软月互动  

  • 咨询反馈
    扫码关注

    PMP、ACP项目管理培训顾问

    思摩特公众号

    返回顶部