欢迎大家来到思摩特西安PMP培训报名班,今天总结了我们部分学员的一些易错PMP考试试题给大家分享下。
↑ PMI授权办学资质(11年~12年)↑最新资质在PMI官方网站或者思摩特百度百科查询(十年PMP等项目管理教学保证)
1.Consider the data in the table below. Assume that your project consists only of these three activities. Your estimate at completion is $4,400.00. This means you are calculating your EAC by using which of the following formulas?
Activity |
% Complete |
PV |
EV |
AC |
A |
100 |
2,000 |
2,000 |
2,200 |
B |
50 |
1,000 |
500 |
700 |
C |
0 |
1,000 |
0 |
0 |
a. EAC = AC/EV × BAC
b. EAC = AC/EV × [work completed and in progress] + [actual (or revised) cost of work packages that have not started]
c. EAC = [Actual to date] + [all remaining work to be done at the planned cost including remaining work in progress]
d. EAC =% complete × BAC
考虑到下表中的数据,假设你的项目仅包含ABC三个活动,你估算的EAC是$4,400.00,这意味着你用到了以下哪个公式来计算EAC的?
Activity |
% Complete |
PV |
EV |
AC |
A |
100 |
2,000 |
2,000 |
2,200 |
B |
50 |
1,000 |
500 |
700 |
C |
0 |
1,000 |
0 |
0 |
a. EAC = AC/EV × BAC
b. EAC = AC/EV × [已完成和进行中的工作] + [还未开始工作包的实际 (或更新)成本]
c. EAC = [到目前的AC] + [所有剩余工作的计划成本]
d. EAC =完成工作的百分比 × BAC
2.在组织内部,一些关键职能部门所拥有,或者针对组织而设定的一般管理原则包括以下所有,除了?
A.组织授予的工作职权
B.具有纪律性的行为
C.掌握项目管理技能
D.允许员工参与计划和实施
3.不同的组织架构在项目组织框架中的含义是?
A.组织实现目标的能力
B.项目团队成员的关联程度
C.项目团队成员及与项目经理之间的物理位置接近程度
D.项目经理对团队资源的权力水平