1. Which of the following correctly states the role of the customer?
- A、Ensure that all team members are pursuing a common vision for the project.
- B、Establish priorities so that the highest-valued functionality is always being worked on
- C、Make decisions that lead to a good return on the investment in the project
- D、ls usually a representative from another group or pision
下列哪一项正确地表述客户角色?
- A、确保所有团队成员都了解项目的共同愿景
- B、确定优先事项,确保最高价值优先处理
- C、为项目中更高的投资回报做决策
- D、通常是另一个小组或部门的代表
2. What communication tool should the team scattering in the whole world use to assist communication?
- A、Take part in the meeting personally at intervals,and hold consistent virtual meetings constantly
- B、Hold one review meeting every two weeks
- C、Work together
- D、Increase the amount of e-mail information and reduce meeting time
全球分布的团队应采用哪一种沟通工具来协助沟通
- A、间歇性的亲自出席会议,持续一致虚拟会议
- B、每两周召开一次回顾会议
- C、集中办公
- D、增加电子邮件信息的数量,加上减少会议时间
3. You have identified a technical risk with a probability of 20% and Size of Loss as 12 days. What is the Risk Exposure?
- A、2.4
- B、0.2
- C、1.2
- D、0.6
你确定了一个可能性为 20%的技术风险,损失时间规模为 12 天。风险暴露为多少?
- A、2.4
- B、0.2
- C、1.2
- D、0.6