    01、The project manager has a list of success criteria provided by different stakeholders at the beginning of the project.The project manager is uncertain how to prioritize the success criteria and must present the project charter in a 

    meeting tomorrow.

    What should the project manager do next?

     

    A. Discuss the success criteria with the stakeholders at the next project meeting

     

    B. List all success criteria in the project charter

     

    C. Select one of the success criteria and include it in the project charter

     

    D. Check with the sponsor about the project success critical and add it to the project charter

     

    项目经理拥有一份在项目开始时由不同相关方提供的成功标准清单。项目经理对于如何排列这些成功标准的优先顺序感到不确定,并且明天必须在会上陈述项目章程。

     

    项目经理接下来应该怎么办?

     

    A、在下一次项目会议上,与相关方讨论成功标准

     

    B、在项目章程中列出所有成功标准

     

    C、选择其中一个成功标准,并将其包含在项目章程中

     

    D、与发起人核对项目成功标准,并将其添加到项目章程中

    厦门PMP网课班在线模拟题1

    02、At the beginning of a project, the project manager sets up the integrated change control system. For this system, a change request is required for any change that will affect which of the following?

     

    A. Resources, timeline, cost, and risk mitigation

     

    B. Planning, timeline, cost, and quality

     

    C. Resources, timeline, cost , and quality

     

    D. Resources, risk mitigation, cost, and quality

     

    项目经理在项目之初建立了综合性变更控制系统。使用该系统时,对下列哪些内容造成影响的变更需要提出变更请求?

     

    A、资源、时间表、成本和风险缓解

     

    B、规划、时间表、成本和质量

     

    C、资源、时间表、成本和质量

     

    D、资源、风险缓解、成本和质量

    厦门PMP网课班在线模拟题2

    03、A customer initiates a new strategic project, which must be completed by the end of the year. The project is critical to the strategic success of the customer. An idea about the scope, budget, and timeline has already been discussed.

     

    What else should be included in the project charter?

     

    A. Approved budget, named resources, and fixed-end date

     

    B. Quantified risks, limits and exclusions, and revised milestone dates

     

    C. High-level requirements, high-level risks, and identified scope

     

    D. Project plan, scope plan, and resource plan

     

    客户启动了一个新的战略项目,该项目必须在年底前完成。该项目对于客户的战略成功至关重要。关于项目的范围、预算和进度已经讨论过。

     

    项目章程中还应包含哪些内容?

     

    A、批准的预算、指定的资源和固定的完工日期

     

    B、定量的风险、限制和例外情况,以及修订的里程碑日期

     

    C、总体要求、主要风险和识别的范围

     

    D、项目计划、范围计划和资源计划

    厦门PMP网课班在线模拟题3

     

    热门推荐

    分享到 更多
  • PMI®, PMP®, PMI-ACP® and PMBOK® are registered marks of the Project Management Institute, Inc.

    电话:025-84547600 / 13390908908 / 400-805-8908 / 传真:025-84547600 / 邮箱:welcome@smartpm.com.cn / Weixin:13327831928

    Copyright © 2009-2024 南京思摩特企业管理咨询有限公司 版权所有  苏ICP备11012816号-2   苏公网安备 32011402010832号

    技术支持:软月互动  

  • 咨询反馈
    扫码关注

    PMP、ACP项目管理培训顾问

    思摩特公众号

    返回顶部