1. Three strategies that typically deal with negative risks or threats are:
A. Enhance, Share, and Accept
B. Transfer, Exploit, and Accept
C. Avoid, Transfer, and Exploit
D. Avoid, Transfer, and Mitigate
1. 三种应对消极风险或威胁的典型策略是( )。
A. 提高、分享和接受
B. 转移、开拓和接受
C. 回避、转移和开拓
D. 回避、转移和减轻
2. A tool that provides a visual representation of human resource allocation to a project, number of working hours, and availability on the project is a:
A. Resource Histogram
B. Staff release plan
C. Resource Breakdown Structure (RBS)
D. Organization Breakdown Structure (OBS)
2. 提供对项目的人力资源分配、工作时间数和项目可用性的可视化演示的工具是:
A. 资源直方图
B. 人员释放计划
C. 资源分解结构RBS
D. 组织分解结构OBS
3. Lee is the project manager of a project, and he is planning responses to a set of risks. As a direct result of implementing these risk responses, he anticipates certain other risks to arise. These are:
A. Secondary risks
B. Primary risks
C. Planned risks
D. Workaround
3. 李是一个项目的项目经理,他正在规划应对一系列风险。作为实施这些风险应对的直接结果,他预计会出现某些其他风险。这些是:
A. 次生风险
B. 主要风险
C. 规划的风险
D. 权变措施