1.At a review meeting, the agile project team realized that it would not be able to complete the full release of the to-do list within the agreed deadline. What should the team do?
- A. How many more team members are needed to complete the calculation
- B. Communicate a new completion date estimate with product owner
- C. Prioritize the to-do list and delete the least valuable stories
- D. Negotiate scope and schedule with product owner
在一次评审会议上,敏捷项目团队意识到在约定期限内将不能按时完成全面发布待办列表事宜。团队应该怎么做?
- A、计算完成还需要多少名团队成员
- B、与产品负责人沟通一个新的完工日期估算
- C、对待办列表重新排列优先顺序,并删除最没有价值的故事
- D、与产品负责人一起协商范围和进度计划
2.A question raised by a team member attracted the attention of the team leader. What should the team leader do?
- A. Let the team solve the problem
- B. Seek guidance from functional managers
- C. Resolve the issue and inform the team
- D. Have the product owner work together to resolve the issue and inform the team
一个团队成员提出的一个问题,引起了团队领导的注意。该团队领导应该怎么做?
- A、让团队来解决这个问题
- B、寻求职能经理的指导
- C、解决这一问题,并通知团队
- D、让产品负责人一起解决这一问题,并通知团队
3.The srum team has two developers: a subject matter expert (SME) and a senior developer. Which method should be used to estimate the story size?
- A. Subject matter experts (SMEs) have expertise in relevant fields and should estimate story size
- B. Senior developers have most development experience and should estimate story size
- C. Subject matter experts (SMEs) and senior developers should work together to estimate story size
- D. Each member should work with each other and form a team to estimate the scale together
Scrum 团队有两名开发人员:一名主题专家(SME)和一名高级开发人员。哪种方法应用于估算故事规模?
- A、主题专家(SME)拥有相关领域的专业知识,应该估算故事规模
- B、高级开发人员拥有大多数开发经验,应该估算故事规模
- C、主题专家(SME)和高级开发人员应该一起估算故事规模
- D、每个成员应互相合作,并形成团队一起估算规模