欢迎大家来到思摩特乌鲁木齐PMP培训班,今天总结了我们部分学员的一些易错PMP考试试题给大家分享下
1. Which of the following is NOT a knowledge management tools and technique?
A. Networking
B. Change requests
C. Knowledge fairs and cafes
D. Story telling
1. 以下哪一个不是知识管理工具和技术?
A. 人际交往
B. 变更请求
C. 知识集市和咖啡馆
D. 讲故事
2. Which of the following statements correctly define the 100 percent rule for WBS?
A. The project is only considered complete once all requirements defined in the original scope statements have been completed.
B. The project is only considered complete once all requirements in the last approved scope baseline have been completed.
C. The final deliverables should fully conform to product requirements; nothing less, nothing more.
D. The total of the work at the work package level should roll up to the higher levels so that nothing is left out and no extra work is performed.
2. 下列哪个选项正确地定义了WBS的100%规则?
A. 只有在原始的范围声明中定义的所有需求完成之后,项目才被认为是完整的
B. 项目只在最后批准的范围基线的所有要求完成后才被认为是完整的
C. 最终交付物应完全符合产品要求,不多也不少
D. 工作包级别的工作总量应该向上滚动到较高的水平,这样就不会遗漏任何东西,也不会执行额外的工作
3. As part of your resource management plan, you have created a chart indicating the number of hours (Y-axis) that a senior programmer will be working over the months (X-axis) of the project. This is an example of a:
A. Pareto Chart
B. Ishikawa Diagram
C. Resource Histogram
D. Staff Acquisition Chart
3. 作为资源管理计划的一部分,你已经创建了一个图表,说明高级程序员将在项目的几个月(x轴)上工作的小时数(y轴)。这属于以下哪种例子:
A. 帕累托图
B. 石川图
C. 资源直方图
D. 人员招募表