欢迎来到思摩特项目管理官方网站! 南京 | 镇江 | 扬州 | 常州 | 芜湖 | 马鞍山 | 滁州 等地区指定项目管理培训中心

加入收藏

    联系我们
  • 全国24小时免费咨询电话:
    400-805-8908

    welcome@smartpm.com.cn

    • 芜湖PMP考试报名培训班|模拟试题分享

  • 发布时间:2019-10-08 10:15:20  来源:思摩特 www.smartpm.com.cn  浏览量:0
  • 编辑导读:思摩特芜湖PMP考试报名培训班模拟试题分享

    欢迎大家来到思摩特芜湖PMP考试报名培训班,今天总结了我们部分学员的一些易错PMP考试试题给大家分享下。

    思摩特PMP办学资质

    ↑ PMI授权办学资质(11年~12年)↑最新资质在PMI官方网站或者思摩特百度百科查询(十年PMP等项目管理教学保证

     

    1. During a presentation to management, you want to display the project schedule with only the key deliverables displayed. What is the correct tool for this purpose ?

    A. Project schedule network diagram 

    B. Critical path network 

    C. Milestone chart 

    D. Critical chain diagram 

    1. 在向管理层汇报期间,你想仅仅展示带有关键可交付成果的项目进度计划,什么是满足该目的的正确工具?

    A. 项目进度网络图

    B. 关键路径网络

    C. 里程碑图

    D. 关键链图

    芜湖PMP考试报名培训班在线模拟题1

    2. The term Progressive Elaboration incorrectly represents which of the following? 

    A. Scope creep 

    B. Rolling wave planning 

    C. Detailing out the product requirements developed during the initiation process. 

    D. Production of fabrication and construction drawings from the design drawings for a chemical plant. 

    2. 以下哪一项是代表渐进明细术语的错误说法?

    A. 范围蔓延

    B. 滚动式规划

    C. 详细说明在启动过程中开发的产品要求

    D. 从化工厂的设计图生成制造图和施工图。

    芜湖PMP考试报名培训班在线模拟题2

     

    3. A project manager feels the need of updating one of the project supplier contracts to meet the project’s current needs. However, before any change requests, the project manager must know the tight process to incorporate a change into this specific contract. What should he do first?

    A. Issue the change request and get it approved through Integrated Change Control process 

    B. Update the project procurements management plan 

    C. Review the change request handling procedure as documented in the contract itself 

    D. Review alternative dispute resolution (ADR) procedures in the contract

    3. 项目经理感到需要更新其中一个供应商的合同以满足项目当前的需要。然而,在做出任何变更请求之前,项目经理必须知道与合同变更密切相关的过程,以便将变更纳入特定的合同中。他应该首先做什么?

    A. 提交变更请求,并且通过整体变更控制过程获得批准

    B. 更新项目采购管理计划

    C. 审查记录在合同本身中的变更控制程序

    D. 审查合同中的替代争议解决方案(ADR)

    芜湖PMP考试报名培训班在线模拟题3

    热门推荐

    分享到 更多
  • PMI®, PMP®, PMI-ACP® and PMBOK® are registered marks of the Project Management Institute, Inc.

    电话:025-84547600 / 13390908908 / 400-805-8908 / 传真:025-84547600 / 邮箱:welcome@smartpm.com.cn / Weixin:13327831928

    Copyright © 2009-2024 南京思摩特企业管理咨询有限公司 版权所有  苏ICP备11012816号-2   苏公网安备 32011402010832号

    技术支持:软月互动  

  • 咨询反馈
    扫码关注

    PMP、ACP项目管理培训顾问

    思摩特公众号

    返回顶部