欢迎大家来到思摩特芜湖PMP考试认证培训,今天总结了我们部分学员的一些易错PMP考试试题给大家分享下。
1. You have a schedule activity that can be delayed without delaying the early start date of any subsequent activities. This is an example of
A. Free Float
B. Lead Float
C. Total Float
D. Lag Float
1.你有一个进度活动,可以在不延迟任何后续活动的最早开始日期的情况下延期。这是以下哪种例子:
A. 自由浮动
B. 提前浮动
C. 总浮动
D. 滞后浮动
2. Which of these statements is true?
A. The cost of correcting mistakes through an inspection is much less than the cost of preventing them.
B. The cost of preventing mistakes is generally much less than the cost of correcting them as revealed by inspection.
C. It does not matter where a defect is captured as long as the finished work product does not have a defect.
D. The cost of correcting mistakes through an inspection is more or less the same as the cost of preventing them since the same effort goes into both activities.
2. 哪一种说法是正确的?
A. 通过检查纠正错误的成本远远低于预防错误发生的成本
B. 预防错误的成本通常要比通过检查发现错误的成本低得多
C. 只要完成的工作产品没有缺陷,缺陷在哪里被捕获并不重要
D. 通过检查来纠正错误的成本或多或少与预防它们的成本相同,因为相同的努力都投入到这两种活动中
3. Jack is the project manager of a project that is halfway through its execution. He is currently looking at the work schedule. He adjusts a few of the schedule milestones and imposes date constraints for some of the work packages. This relates to which of the following processes.
A. Control Quality
B. Develop Schedule
C. Control Scope
D. Control Schedule
3. 杰克是一个项目的项目经理,这个项目已经完成了一半。他目前正在查看工作时间表。他调整了一些时间表的里程碑,并对一些工作包施加了日期限制。这与下列哪个过程有关。
A. 控制质量
B. 制定进度计划
C. 控制范围
D. 控制进度