1. A SPIKE is undertaken in which phase of an Agile project?
A、Planning
B、Analysis
C 、Design
D、Testing
SPIKE 是在哪个敏捷项目阶段?
A、规划
B、分析
C、设计
D、测试
2. Which of the following is an INCORRECT statement about Story Points?
A 、Story points rely on analogous estimation
B 、Story points measure the size and complexity of a story
C、Story points are a pure measure of size
D、Story points can be easily compared across teams
下列哪一项关于故事点的叙述是错误的?
A、故事点依靠于类比估计
B、故事点测量故事的大小和复杂性
C、故事点是关于规模大小的度量
D、故事点可以很容易地跨团队比较
3. When one new team member is invited to take part in on Delphi Plan Con ference and the agile team leader notices that the member is not familiar with the process,how should the
leader do?
A、Require that the team member should take part in Delphi meeting frequently to obtain experience
B、Set up a plan and train team members the agile tools and approaches
C、Set up one project vocabulary dictionary,and deliver to all team members
D、In the face-to-face Delphi meeting,encourage new team members to raise questions
一名新团队成员应邀参加一次德尔菲计划会议,敏捷团队领导( the agile team leader)注意到该成员对这个过程并不熟悉,敏捷团队领导应该怎么做?
A、要求该团队成员频繁参加德尔菲会议,以便获得经验
B、创建一份计划,为团队成员培训敏捷工具和方法
C、创建一个项目词汇字典,并发给所有团队成员
D、在面对面的德尔菲会议中,鼓励新的团队成员提问题