1、What typically occurs directly after an agile team and product owner build an initial product roadmap?
A.Release planning
B. Definition of the product vision
C.Exploratory 360
D.Iteration planning
当敏捷团队和产品负责人在完成初始路线图后,一般接下来要进行什么活动?
A.发布计划
B.产品前景的定义
C.探索性 360
D.迭代计划
2、What is Cohn' s definition of product knowledge
A. intrinsic knowledge of the product domain and industry
B. knowledge about what the threshold features are about a product
C. extrinsic knowledge of the product domain and industry
D. knowledge about what features will or will not be developed in a project
Cohn 对于产品知识的定义是什么?
A.产品领域和工业的内部知识
B.产品入门特征知识
C.产品领域和工业的外部知识
D.在项目中什么特征会或不会被开发
3、In scrum a change report is used to document a change in scope . When is a change report typically created ?
A. During release planning
B. Immediately after any scope change
C.After a sprint
D. During sprint planning
在 Scrum 中的变更报告是用来记录范围变更。通常创建一个变更报告是在何时?
A.在发布计划期间
B.任何范围变更后的第—时间
C.冲刺后
D.在冲刺计划期间