欢迎大家来到思摩特潍坊PMP考试认证培训,今天总结了我们部分学员的一些易错PMP考试试题给大家分享下。
1. Robert wants to assign a risk owner for every project risk for which a risk response action is planned. Where must he update this information?
A. Resource management plan
B. Risk register
C. Stakeholder register
D. Project charter
1. 罗伯特希望为每个项目风险分配一个风险责任人,以执行风险响应行动计划。他必须在哪里更新这些信息?
A. 资源管理计划
B. 风险登记册
C. 相关方登记册
D. 项目章程
2. Ben is the project manager for a mobile application development project. Due to a recent technological development, a significant change in product design is required. This change would require a 25 percent increase in the project budget. Ben prepares a detailed report and emails it to the project sponsor, and the sponsor acknowledges the receipt of the report. What should Ben do next?
A. Update the cost management plan
B. Update the project budget
C. Update the project schedule
D. Wait for the formal approval of the new budget
2. Ben是一个移动应用开发项目的项目经理。由于最近的技术发展,需要对产品设计进行重大变革。这一变革将需要增加25%的项目预算。Ben准备了一份详细的报告和电子邮件,项目的发起人已经确认收到报告。接下来本应该做什么?
A. 更新成本管理计划
B. 更新项目预算
C. 更新项目进度
D. 等待新预算的正式批准
3. Which of the following processes produces a Risk Register?
A. Perform Quantitative Risk Analysis
B. Plan Risk Management
C. Perform Qualitative Risk Analysis
D. Identify Risks
3. 下列哪个过程会产生风险登记册?
A. 实施定量风险分析
B. 规划风险管理
C. 实施定性风险分析
D. 识别风险