欢迎大家来到思摩特潍坊PMP培训班,今天总结了我们部分学员的一些易错PMP考试试题给大家分享下:
1. If you want to compress a project schedule, what are two of the recommended alternatives to consider?
A. Fast Tracking and Schedule Network Analysis
B. Crashing and Fast Tracking
C. Resource Levelling and What-If Scenario Analysis
D. Crashing and Schedule Network Analysis
1. 如果你想压缩项目进度,考虑哪两种推荐的备选措施?
A. 快速跟进和进度网络分析
B. 赶工和快速跟进
C. 资源平衡和假设情景分析
D. 赶工和进度网络分析
2. Large organizations typically manage a wide range of projects; from small projects to large initiatives requiring long-term commitments. Which of the following factors can be used in scaling such projects:
A. Team size, geographical distribution, regulatory compliance, organizational complexity, technical complexity, and funds availability.
B. Team size, geographical distribution, regulatory compliance and organizational complexity.
C. Team size, geographical distribution and regulatory compliance.
D. Team size, geographical distribution, regulatory compliance, organizational complexity and technical complexity.
2. 大型组织往往管理大量的项目,从小型项目到需要长期承诺的大型项目。以下哪些是针对这些项目需要考虑的规模化参数( )?
A. 团队大小、地理分布、法规合规性、组织复杂性、技术复杂性和可用资金
B. 团队大小、地理分布、法规合规性、组织复杂性
C. 团队大小、地理分布、法规合规性
D. 团队大小、地理分布、法规合规性、组织复杂性、技术复杂性
3. Which of the following is not a part of the data gathering tools used in Control Quality process?
A. Checklists
B. Control Chart
C. Check sheets
D. Statistical sampling
3. 以下哪一项不是控制质量过程的数据收集技术?
A. 核对单
B. 控制图
C. 核查表
D. 统计抽样