1.Agile team is developing a complex product in iteration. In the third iteration, the product owner found a problem. What should the product owner tell the team?
- A. Create a difficult spy story
- B. Continue adding features because the iteration has started
- C. Cancel and reschedule sprint
- D. Increase the sprint length because additional features have been added
敏捷团队在迭代中,正开发一个复杂的产品。在第三次迭代中,产品负责人发现了一个问题。产品负责人应该告诉团队什么?
- A、创建一个难点刺探故事
- B、继续添加功能,因为迭代已开始
- C、取消并重新计划 Sprint
- D、增加 Sprint 长度,因为添加了额外功能
2.The agile project team received an urgent request during the iteration. What should agile project managers do first?
- A. Stop working on the unfinished user story and work on the request first
- B. Call a team meeting to change the iteration scope to include the request
- C. Provide project team suggestions to customers
- D. Explain that the team cannot include the request until the next iteration
敏捷项目团队在迭代期间收到一个紧急请求。敏捷项目经理首先应该做什么?
- A、停止未完成用户故事的工作,先为该请求工作
- B、召开一场团队会议,更改迭代范围以包含该请求
- C、向客户提供项目团队建议的意见
- D、解释到下一次迭代之前,团队不能包含该请求
3.An external stakeholder wants to be informed of the risks and problems that are coming. What should scrum executives do?
- A. Meet with the external stakeholders to review the risk register
- B. Meet with the external stakeholders to review the project plan
- C. Regularly update the project plan and send it to external stakeholders for review
- D. Direct the external stakeholder to view the source of the information
一名外部干系人希望被告知即将发生的风险和问题。Scrum 主管应该怎么做?
- A、与该外部干系人会面,审查风险登记册
- B、与该外部干系人会面,审查项目计划
- C、定期更新项目计划,并发送给外部干系人审查
- D、指引该外部干系人查看信息发射源