1.How to share the output series plan with stakeholders in agile project?
- A. Using the highest visualization method
- B. Determine what you need to know based on your role needs
- C. According to project communication plan
- D. Through a series of stakeholder meetings
在敏捷项目中,如何与干系人共享输出的系列计划?
- A、用最高可视化的方法
- B、根据角色需求确定哪些需要知道
- C、根据项目沟通计划
- D、通过一系列干系人会议
2.When do you write acceptance tests for user stories?
- A. Coding completed, before acceptance test
- B. After writing user stories, before coding
- C. At the beginning of product to-do prioritization
- D. After the product to-do estimate is completed, but before the iteration plan begins
一般在什么时间点编写用户故事的验收测试?
- A、编码完成,验收测试前
- B、编写用户故事后,开始编码之前
- C、在产品待办事项优先级排序的开始
- D、在产品待办事项估算完成后,但是在迭代计划开始前
3.Which of the following types of meetings does agile cost estimation start with?
- A. Project review
- B. Steering Committee
- C. Release plan
- D. Iteration plan
敏捷的成本估算从以下哪个类型的会议开始?
- A、项目回顾
- B、指导委员会
- C、版本发布计划
- D、迭代计划