欢迎大家来到思摩特台北PMP培训班,今天总结了我们部分学员的一些易错PMP考试试题给大家分享下:
1. Which of these is not a component of the scope baseline that is contained in the project management plan?
A. Work Breakdown Structure (WBS)
B. Requirements documentation
C. WBS Dictionary
D. Project Scope Statement
1. 在项目管理计划中,哪项不是范围基准的组成部分?
A. 工作分解结构(WBS)
B. 需求文件
C. WBS字典
D. 项目范围说明书
2. The agile technique of on-demand scheduling is not suitable when
A. Product deliverables can be incrementally developed.
B. Project requirements can be decomposed into smaller chunks that are relatively similar in size and scope.
C. Project tasks can be bundled by size and scope.
D. The use of a predictive lifecycle is mandated by the customer.
2. 在敏捷项目中,下列哪项按需进度计划是不合适的:
A. 产品可交付物可以增量地开发
B. 项目要求可以分解成较小的部分,大小和范围都比较相似
C. 项目任务可以按大小和范围捆绑
D. 预测生命周期的使用是由客户授权的
3. Project stakeholders are inpiduals and organizations who are actively involved in the project or who have an interest 1fl it. Which of the following is not an internal stakeholder?
A. Program Manager
B. Project Sponsor
C. Competitor
D. Project Manager
3. 项目相关方是积极参与项目的个人和组织,或者是有兴趣参加的人。以下哪一个不是内部相关方?
A. 项目集经理
B. 项目发起人
C. 竞争对手
D. 项目经理