1. Which of the following is NOT true about SCRUM?
- A、Only active participants in the sprint (not interested observers or removed stakeholders) may speak during the daily scrum meeting
- B、A sprint planning meeting is held midway of each sprint.
- C、The Product Owner prioritizes the product backlog
- D、Only two hours may be spent preparing for the sprint review,for a two weeks sprint
以下哪一项关于敏捷开发的描述是错误的?
- A、只有在冲刺阶段的积极参与者(而不是观察者)能够在每日立会中发言
- B、在迭代进行中开迭代规划会议
- C、产品所有者负责待办事项中的优先级排序
- D、对一个为期两周的冲刺来说,只有两个小时的时间来进行冲刺回顾
2. When agile team is preparing for a large-scale story that involves huge structural risks,because the next iteration has been planned,how should the project agile manager solve the problem?
- A、Delay the story work and keep the team’s speed
- B、Re-check the demands and set up detailed norms
- C、Add the story in risk registration brochure and analyze with customers
- D、Implement investigation so as to better review the risk
敏捷团队正在准备从事一个牵涉架构风险的大规模故事,由于下一个迭代已经计划完毕,该项目敏捷管理师应该如何解决这个风险?
- A、延迟该故事的工作,保持团队速度
- B、重新查阅需求,创建详细的规范
- C、在风险登记册中添加该故事,并与客户一起分析
- D、执行考察工作,以更好的回顾该风险
3. Agile project team needs to revise contract with one supplier and customize one integrationtool for project establishment. What should project team do to plan and monitor supplier’s work?
- A、Supplier’s project plan and monthly state report.
- B、Agile release plan and daily standup meeting
- C、Agile iteration plan and review meeting
- D、Daily task planning and updating of E-mail’s state
敏捷项目团队与一个供应商修订合同,定制一个作为项目组建的集成工具,项目团队应该做什么来计划和监控供应商工作?
- A、供应商的项目计划和每月状态报告
- B、敏捷发布计划和每日站会
- C、敏捷迭代计划和回顾会议
- D、每日任务规划以及电邮的状态更新