1. A technique that calculates multiple project durations with different sets of activity assumptions and variables is:
A. Process Analysis
B. Theoretical Analysis
C. Simulation
D. Effect Analysis
1. 一种用不同的系列的活动假设和变量来计算项目多种持续时间的技术是:
A. 过程分析
B. 理论分析
C. 模拟分析
D. 影响分析
2. You are in the initiation phase of your project, and you believe the project can be completed for $100,000. However, you are an experienced project manager and know that many things can happen between the initiation phase and the closure of the project. In the project charter, you have provided an estimate of $75,000 to $175,000. This is an example of:
A. Narrow Estimate
B. Absolute Estimate
C. Rough Order of Magnitude Estimate
D. True Estimate
2. 你处于项目的启动阶段,你相信项目能够以10万美元完成。但是,你是一个有经验的项目经理,并且知道在项目启动阶段和收尾项目之间会发生很多事情。在项目章程中,你提供了7.5万至17.5万美元的估算。这是以下哪种例子:
A. 窄带估算
B. 绝对估算
C. 粗略量级估算
D. 真实估算
3. Communication noise refers to influences on effective communication that influence the interpretation of conversations. Noise affects which components of communication?
A. Encoding and decoding
B. Decoding and feedback
C. Transmission and decoding
D. Encoding and feedback
3. 沟通噪声是指干扰回话对有效沟通产生的影响。噪声影响沟通的哪些部分?
A. 编码和解码
B. 解码和反馈
C. 传输和解码
D. 编码和反馈