欢迎大家来到思摩特深圳PMP培训中心,今天总结了我们部分学员的一些易错PMP考试试题给大家分享下:
1. In projects where there is a gap between the real business requirements and the stated business requirements, agile methods are extremely helpful. Agile methods provide a solution to this problem by:
A. Completing the project quickly so that gap is significantly reduced.
B. Replacing the project manager with a Scrum master in order to expedite the project.
C. Purposefully building and reviewing prototypes and release versions to refine requirements.
D. Eliminating the documentation altogether from the project management approach.
1. 在实际业务需求与已声明的业务需求之间存在差距的项目中,敏捷方法非常有用。敏捷方法为这个问题提供了一个解决方案:
A. 快速完成项目,使差距显著缩小
B. 用敏捷教练替换项目经理,以加快项目的进度
C. 有目的的建立和审查原型和发布版本以细化需求
D. 从项目管理方法中完全消除文档
2. Which of the following should be avoided while applying logical relationships to project activities:
A. Applying the SS relationship with a lead
B. Applying the SS relationship with a lag
C. Applying the SF relationship
D. Applying multiple relationships between the same activities
2. 在将逻辑关系应用于项目活动时,应避免下列哪一项:
A. 使用带有提前量的SS关系
B. 使用带有滞后量的SS关系
C. 使用SF关系
D. 在同一活动中应用多重关系
3. When possible, the detailed project schedule( ) throughout the project to adjust for knowledge gained, increased understanding of the risk, and value-added activities.
A. Should stand firm
B. Should remain flexible
C. Must be avoided
D. Must be inflated
3. 在可能的情况下,详细的项目计划( )以便根据获得的知识进行调整,增加对风险的理解,以及增值活动。
A. 应该立场坚定
B. 应该保持灵活
C. 必须避免
D. 必须被夸大