欢迎大家来到思摩特沈阳PMP,今天总结了我们部分学员的一些易错PMP考试试题给大家分享下。
↑ PMI授权办学资质(11年~12年)↑最新资质在PMI官方网站或者思摩特百度百科查询(十年PMP等项目管理教学保证)
1、Which of the following typically occurs during the project's closing phase?
A. Measure customer satisfaction, draft the final project report, and apply final project scope changes
B. Obtain administrative closure, transfer team resources, balance the project budge and archive project documentation
C. Create the lessons learned report, update key stakeholders and ensure that final deliverables conform to established quality standards
D. Administer the acceptance process, capture lessons learned, prepare the finally project reports and transfer team members
在项目收尾阶段通常会发生下列哪一项?
A.测量客户满意度,起草最终项目报告并应用最终项目范围变更
B.获得行政收尾,转让团队资源,平衡项目预算并将项目文档存档
C.创建经验教训报告、更新关键相关方并确保项目可交付成果符合制定的质量标准
D.管理验收过程、收集经验教训、准备最终项目报告并转移团队成员
2、You are assigned as a project manager to lead a new quality improvement project. Management is asking for a plan. Which of the following should you create FIRST?
A.Scope statement
B.Quality plan
C.Schedule
D.Project plan
你被分配为一个新的质量改进项目的项目经理。管理层要求创建一个计划。下面哪项你必须首先创建?
A.范围说明书
B.质量计划
C.进度表
D.项目管理计划
3、 As a project approaches completion:
A. Risk management is no longer needed
B. The cost of changes typically increase
C. The probability of high-risk items increases
D. Contingency reserves are no longer needed
当项目接近完工时:
A.就不再需要风险管理
B.变更成本一般会增加
C.高风险项的肯能性会增加
D.不再需要应急储备