欢迎大家来到思摩特上海PMP培训报名班,今天总结了我们部分学员的一些易错PMP考试试题给大家分享下。
↑ PMI授权办学资质(11年~12年)↑最新资质在PMI官方网站或者思摩特百度百科查询(十年PMP等项目管理教学保证)
1.客户向项目经理提供了一份需求清单。看完该清单后,项目经理安排了一次征集意见的会议,向关键项目相关方介绍清单内容,并提供了最近刚收尾的类似项目文件信息。此类会议属于下列哪个过程组的组成部分?
1.The customer has given a list of requirements to the project manager. After reviewing the list, the project manager coordinates a meeting in order to be introduced, to present the list to key stakeholders and to present information from a similar recently closed project file.This type of meeting is part of what process?
A.项目启动 Initiating a project
B.项目收尾 Closing a project
C.采购管理 Procurement management.
D.创建WBS Create a WBS
2.You are managing a project that has five subcontractors. You must monitor contract performance, make payments, and manage provider interface. One subcontractor submitted a change request to expand the scope of its work. You decided to award a contract modification based on a review of this request. All these activities are part of—
a. Control procurements
b. Conduct procurements
c. Form contract
d. Configuration management
2.你正在管理一个有5家分包商的项目,你必须监控供应商的绩效,付款和管理供应商界面。一家分包商提交了一份变更请求增加了项目范围。在审核了这份变更之后你决定奖励一家承包商。所有这些活动都是以下哪项的一部分?
A.控制采购
B.实施采购
C.签订合同
D.配置管理
3.请问以下哪一项符合PMI人才三角形?
A.项目管理技术,行业技术,领导力
B.项目管理技术,领导力,战略和经营管理
C.项目管理技术,影响力,战略和经营管理
D.行业技术,领导力,战略和经营管理