欢迎大家来到思摩特上海PMP培训机构,今天总结了我们部分学员的一些易错PMP考试试题给大家分享下
1. Which of these types of precedence relationships is least commonly used in the Precedence Diagramming Method?
A. Start to Start
B. Finish to Finish
C. Finish to Start
D. Start to Finish
1. 在前导图法(PDM)最少使用的紧前关系是()?
A. SS
B. FF
C. FS
D. SF
2. A RACI chart is an example of a ( ).
A. Network
B. Flowchart
C. Responsibility assignment matrix
D. Hierarchical-type organization chart
2. RACI图是一个( )的例子。
A. 网络
B. 流程图
C. 责任分配矩阵RAM
D. 层级型组织图
3. If the project’s current total earned value (EV) is $100,000 and the actual amount spent (AC) is $95,000, what is the cost variance of the project?
A. The cost variance is $1.05
B. The cost variance is $5,000
C. The cost variance is $0.95
D. The cost variance is $-5,000
3. 如果项目当前总的EV是$100,000,累计的AC是$95,000。项目的成本偏差是多少()?
A. CV = $1.05
B. CV = $5,000
C. CV = $0.95
D. CV = $-5,000