1.What is the purpose of using labels and prompts between different stages in Kanban production?
- A. Help to carry out drum buffer rope process
- B. To prompt the previous phase to generate more work
- C. To inform external suppliers of current production status
- D. In order to maximize the number of work in process (WIP) in the system
在看板制作过程中,在不同阶段之间使用标签和提示的目的是什么?
- A、有助于执行鼓—缓冲—绳法过程
- B、为了提示前面的阶段以产生更多的工作
- C、为了告知外部供应商当前生产状态
- D、为了最大化系统中的在制品(WIP)的数量
2.Stakeholders and agile team members recognize that the vision statement is constantly changing, resulting in changing perceptions of the vision. What should the team do What do you do?
- A. Create a project charter for stakeholders with a vision for the team
- B. Have stakeholders create a vision statement that will remain unchanged
- C. In the project brief, update the vision and agree on common terms
- D. Using information collection technology to solicit project vision
干系人和敏捷团队成员识别到愿景陈述不断发生变化,造成对愿景的看法也发生变化。团队应该怎么做?
- A、为干系人创建一份项目章程,包含针对团队的愿景
- B、让干系人创建一份将保持不变的愿景陈述
- C、在项目概况说明书中,更新愿景,并约定共用术语
- D、利用信息收集技术,征求项目愿景
3.Agile teams fulfill their commitments, but feel that they can improve speed. How can team members achieve this goal?
- A. Bring simpler stories into sprint
- B. Reduce unproductive time
- C. Move user stories to another sprint
- D. Identify key processes to improve
敏捷团队履行其承诺,但感觉能够提高速度,团队成员如何能够实现这一占?
- A、将较为简单的故事拉进 Sprint 中
- B、减少非生产性时间
- C、将用户故事移到另一个 Sprint 中
- D、识别关键过程以改进