01、A team member request to change progress of a project activity, which of the following measure should the project manager take?
A. Ask team members to provide the new schedule to complete the activity, and prepare a change request
B. Team meetings to determine what other activities may delay, and then prepare a change request
C. Ask to complete the activity also need how much time and money, and then prepare a change request
D. Obtain customer approval, team meetings, and prepare change requests
一名团队成员要求更改某个项目活动的进度,项目经理应该采取下列哪一项措施?
A、要求团队成员提供新的时间表来完成活动,并准备一份变更请求
B、与团队开会,确定还有哪些其他活动可能会延迟,然后准备一份变更请求
C、询问完成该活动还需要多少时间和资金,然后准备一份变更请求
D、获得客户批准,与团队开会,并准备变更请求
02、Which of the following circumstances would hinder project closure?
A. The operational support is not complete
B. The project management office did not approve the communications plan
C. The project has been cancelled
D. The client did not approve all agreed upon deliverables
下列哪一种情况会妨碍项目收尾?
A、运营支持不完备
B、项目管理办公室未批准沟通计划
C、项目已被取消
D、客户不批准所有约定的可交付成果
03、A project experiences issues and a correction is required. The project manager assesses the impact of the corrections and performs which of the following activities?
A. Request a change control meeting
B. Implement corrective actions
C. Update the risk register based on impact
D. Re-baseline the schedule based on impact
一个项目发生问题,需要纠正。项目经理评估纠正的影响,并执行下列哪一项活动?
A、请求召开变更控制会议
B、执行纠正措施
C、根据影响更新风险登记册
D、根据影响重订进度基准