欢迎大家来到思摩特南昌PMP远程培训班,今天总结了我们部分学员的一些易错PMP考试试题给大家分享下。
↑ PMI授权办学资质(11年~12年)↑最新资质在PMI官方网站或者思摩特百度百科查询(十年PMP等项目管理教学保证)
1. Martin is the project manager of a project that is in an early phase. He needs to estimate costs but finds that he has a limited amount of detailed information about the project. Which of the following estimation techniques is least suited to his requirements?
A. Top-down Estimating
B. Bottom-up Estimating
C. Analogous Estimating
D. Budgetary Estimating
1. 马丁是一个处于项目早期阶段的项目经理。他需要估算成本,但他发现所拥有的项目详细信息有限。下列哪种估算技术最不适合他的要求?
A. 自上而下
B. 自下而上
C. 类比估算
D. 预算估算
2. Most project management software packages use a method of constructing a project schedule network diagram known as:
A. Waterfall Method
B. Precedence Diagramming Method
C. Agile Method
D. Just-in-time Method
2. 大多数项目管理软件包使用一种构建项目进度网络图的方法,称为:( )
A. 瀑布方法
B. 紧前关系绘图法
C. 敏捷方法
D. 拉动式方法
3. Which of the following processes produces a work breakdown structure as an output?
A. Create WBS
B. Define Scope
C. Develop Project Management Plan
D. Define Activities
3. 以下哪一个过程的输出是工作分解结构WBS?
A. 创建WBS
B. 定义范围
C. 制定项目管理计划
D. 定义活动