1. Under which of the following scenarios would you not use a decision tree?
A. When some future scenarios are unknown
B. When you need to look at the implications of not choosing certain alternatives
C. When the future scenarios are known
D. When the outcomes of some of the actions are uncertain
1. 以下何种情景下,你不会使用决策树?
A. 当一些未来的场景未知时
B. 当你需要考虑不选择某些备选方案的含义时
C. 当未来的场景已知时
D. 当某些行为的结果不确定时
2. What is the best way to make an accurate forecast of ETC?
A. EAC – AC
B. BAC – EV
C. Manual forecasting of cost of the remaining work.
D. (BAC – EV)/CPI
2. 做出对ETC准确预测最好的方式是什么?
A. EAC – AC
B. BAC – EV
C. 人工预测剩下工作的成本
D. (BAC – EV)/CPI
3. In a project, Activity A has a duration of four days and begins on the morning of Monday the fourth. The successor Activity, B, has a Finish-to- Start (FS) relationship with A. The Finish-to-Start relationship has two days of lag, and Activity B has a duration of three days. If Saturday and Sunday are non-working days, which of the following statements is true?
A. Total elapsed days (completing both activities) is seven days
B. Activity B will be completed by the end of the day on Thursday, the 14th
C. Activity B will be completed by the end of the day on Friday, the 15th.
D. Activity B will be completed by the end of the day on Tuesday, the 12th
3. 在一个项目中,活动A的持续时间为四天,从第星期一(4号)的早晨开始。后继活动B具有与A的完成-开始(FS)关系。完成到开始的关系有两天的延迟,并且活动B的持续时间为三天。如果星期六和星期日是非工作日,下列哪个陈述是正确的?
A. 总共经过的天数(完成两项活动)是7号。
B. 活动B将在星期四结束时完成,是14号。
C. 活动B将在星期五结束时完成,是15号。
D. 活动B将在星期二结束时完成,是12号。