1.Three teams are currently on day 8 of a 2-week sprint. The team speed is 30, and 20 story points have been completed, but the team can only complete another 6 story points. How should the team solve the story point gap?
- A. Add extra tasks to the to-do that represent two story points
- B. Remove the lowest priority task that represents four or more story points from the to-do list
- C. Extend iteration length by two days
- D. Reduce iteration length by two days
有 3 个团队目前正处于一个为期 2 周的 Sprint 的第 8 天。团队速度为 30,有 20 个故事点已经完成,但团队只能额外再完成 6 个故事点。团队应如何解决故事点差距?
- A、在待办事项中添加代表两个故事点的额外任务
- B、从待办事项中删除代表四个或更多故事点的最低优先级任务
- C、延长迭代长度两天时间
- D、减少迭代长度两天时间
2.According to the figure below, what is the current state of the iteration when comparing the planned and completed story points?
- A. Iteration is in danger
- B. The team has deleted the scope
- C. Iteration ahead of schedule
- D. Team speed is stable
根据下图,对比计划的故事点和已完成的故事点时,迭代的当前状态是什么?
- A、迭代处于危险之中
- B、团队已经删除范围
- C、迭代提前于进度
- D、团队速度稳定不变
3.Which of the following statements about epic stories is true?
- A. Epic stories need to be decomposed at the functional boundary
- B. Epic stories are not product specific
- C. Epic stories are user stories that can be completed in one iteration
- D. Epic stories can be broken down into smaller user stories
下列针对史诗故事的说法哪一项是正确的?
- A、史诗故事需要在功能边界分解
- B、史诗故事并不代表产品特办事项
- C、史诗故事是指可以在一次迭代中完成的用户故事
- D、史诗故事可以分解成较小的用户故事