1、As a developer on the agile team , Greg is beginning development on a task . Greg is at the task board and must place the task card in the correct column of the task board to update everyone of its status. In which column should Greg place the task card?
A. To do
B. Ready for testing
C. Done
D. In progress
作为敏捷团队的一员,Greg 开始一个任务的开发。Greg 在任务板前,且必须将任务卡放在任务板正确的一栏去提升每个人的任务状态。Greg 应将任务卡放在哪一栏?
A.即将做
B.准备测试
C.己完成
D.在进展中
2、What project artifact is helpful for testers performing an exploratory test? The artifact gives a brief overview of product functionality.
A. The project roadmap
B. The project vision
C. The project charter
D. The project data sheet
某一项目工件有助于测试者执行探索性的测试,为产品功能提供概述,这一工件是指
A.项目路线图
B.项目前景
C.项目章程
D.项目数据表
3. Which of the following BEST represents the expected outcome of a release planning meeting?
A. A detailed plan with identified deliverables and dependencies, budget reconciled with timelines, constitution of a change-control board to manage scope changes.
B. Detailed Cost, Time, Quality plan, along with exhaustive set of risks identified
C. An aggressive plan that sets tough internal goals and sufficient buffer for external goals
D. A set of stories and epics planned to be delivered during the release, allocated to iterations and a high-level design or approach.
以下哪项是关于发布规划会议的最好预期成果?
A.制定一份关于可交付成果及其属性,详细的预算,可以管理范围变更的变更控制委员会的详细计划
B.详细的成本、 时间、 质量计划,以及整套内容详尽的己知风险
C. 设置有挑战性的内部目标和足够缓冲的外部目标计划
D.把一组将要在发布过程中交付的故事和史诗投放到迭代和高水平设计或方法上