欢迎大家来到思摩特昆明PMP远程培训班,今天总结了我们部分学员的一些易错PMP考试试题给大家分享下。
↑ PMI授权办学资质(11年~12年)↑最新资质在PMI官方网站或者思摩特百度百科查询(十年PMP等项目管理教学保证)
1. Work Performance Data is an important input to the Control Procurements process. Which of the following is not a component of Work Performance Data?
A. Data regarding supplier’s conformance to quality standards
B. Data on completed deliverables
C. Data regarding incurred or committed costs on each supplier contract
D. Data on supplier invoices and respective payments
1. 工作绩效数据是控制采购过程的重要输入。下列哪一项不是工作绩效数据的组成部分?
A. 关于供应商遵守质量标准的数据
B. 关于完成的可交付成果的数据
C. 关于每个供应商合同中发生或承担的费用的数据
D. 关于供应商发票及其支付的数据
2. Which of the following techniques can help a project manager review a supplier’s internal work processes to ensure compliance to standards during the production of the deliverables? (Assume that all of the given choices are available to the project manager.)
A. Audits
B. Performance reporting
C. Contract change control
D. Inspections
2. 下列哪项技术可以帮助项目经理审查供应商的内部工作流程,以确保可交付成果在生产过程中符合标准?
A. 审计
B. 绩效报告
C. 合同变更控制
D. 检查
3. A project manager wishes to illustrate the connections between the work that needs to be done and the project team members. According to the PMBOK. The resulting document is a:
A. Responsibility Assignment Matrix (RAM)
B. Resource Planning Chart (RPC)
C. Task Assignment Model (TAM)
D. Resource Assignment Chart (RAC)
3. 作为项目经理希望说明团队成员和需要完成的工作之间的联系,根据PMBOK,该文件是:( )。
A. 责任分配矩阵RAM
B. 资源规划图RPC
C. 任务分配模型TAM
D. 资源分配图RAC