欢迎大家来到思摩特昆明PMP培训班,今天总结了我们部分学员的一些易错PMP考试试题给大家分享下:
1. With a growing awareness of so-called unknowable-unknowns, the existence of emergent risk is becoming clear. These are risks that can only be recognized after they have occurred. Emergent risks can be tackled through developing:
A. Project resilience
B. Project charter
C. Project management plan
D. Project risk management plan
1. 随着对所谓未知-未知意识的增加,紧急风险的存在性正在变得清楚明了,这些是只有在发生之后才能被认识的风险。紧急风险可以通过制定( )来处置。
A. 项目弹性(韧性)
B. 项目章程
C. 项目管理计划
D. 项目风险管理计划
2. Change control tool selection should be based on the needs of the project stakeholders, including organizational and environmental considerations and/or constraints. Which of the following is not a key change management consideration while selecting an appropriate change control tool for a project?
A. Identifying and selecting a change item
B. Configuration item verification and audit
C. Documenting the change into a proper change request
D. Tracking change requests
2. 变更控制工具的选择应该基于项目相关方的需要,包括组织和环境的因素与/或制约。以下哪一项不是选择项目变更控制工具需要考虑的因素?
A. 识别和选择变更项
B. 配置项核实与审计
C. 将变更记录在核实的变更请求中
D. 追踪变更请求
3. In general, Perform Qualitative Risk Analysis is:
A. Not often completed
B. Complete and 100 percent accurate
C. In-depth and thorough
D. focused on high-priority risks
3. 一般地,实施定性风险分析是:
A. 常不完整
B. 完整并且100%准确的
C. 深入和彻底的
D. 关注高优先级风险