1、When is the best time for an agile team to define the project and quality standards it will use?
A. At the beginning of an effort
B. After the first iteration
C. During the first retrospective
D. After the first release
定义项目和质量的标准的最佳时间是在
A.一项工作的开始
B.首次迭代后
C.首次回顾期间
D. 首次发布后
2、Nathan, a new agile practitioner, is at a planning event where the relative development effort of user stories of a large product backlog is to be estimated. The planning event is mostly conducted in silence and the team is to assign user stories to various t-shirt sizes (small, medium, large, extra-large). The planning event is efficient and the user stories are estimated quickly. What type of planning event is Nathan mostly likely attending?
A. T-shirt estimating
B.Infinity estimating
C.Affinity estimating
D.Relative estimating
敏捷开发者 Nathan,正进行一项计划活动,需要估算一大型产品待办事项中开发用户故事的相对工作量。团队计划将用户故事赋值为不同的 T 恤尺码(小,中,大,加大)来表示开发的工作量。这次计划活动高效并且迅速估算了用户故事。那么 Nathan 最有可能在进行哪一种计划活动?
A.T 恤估算
B.无穷估算
C.亲和估算
D.相对估算
3、Who can give inputs to the team in terms of a list of items to work on?
A.Product Owner
B.ScrumMaster
C.Customer
D.None of the above
在一系列工作上,谁能给团队输入?
A.产品所有者
B.ScrumMaster
C.客户
D.以上都不是