1. Adaptive project lifecycles, in comparison with predictive project lifecycles, are developed with the intent of:
A. Eliminating cost of changes throughout the project’s lifecycle
B. Providing agility in responding to change
C. Maximizing cost of changes throughout the project’s lifecycle
D. Minimizing cost of changes throughout the project’s lifecycle
1. 与预测项目生命周期相比,自适应项目生命周期的开发目的是:
A. 消除整个项目生命周期中的变更成本
B. 在应对变化时提供敏捷性
C. 最大化整个项目生命周期中的变更成本
D. 最小化整个项目生命周期中的变更成本
2. The best practice to gather and document lessons learned is during weekly progress meetings. The agenda can have a lessons-learned brainstorming item at the end of these meetings. You can ask team members to put forward their recommendations, but it is always better to adopt a mote structured way to gather lessons learned. Which of the following approaches will ensure you capture important lessons learned on your project?
A. Planning risk responses
B. Determining estimate to complete
C. Review of project variances
D. Signing off on the minutes of the meeting
2. 他最好的做法是收集并记录每周的进展会议中所吸取的经验教训。在这些会议结束时,议程可以有一个经验教训的头脑风暴议程。你可以要求团队成员提出他们的建议,但是最好采用一种结构化的方式来收集经验教训。下列哪种方法能确保你在项目中获得重要的经验教训?
A. 规划风险应对
B. 确定完工估算
C. 审查项目偏差
D. 签署会议记录
3. Many project managers have seen a graph that shows “Influence of Stakeholders” starting out high and declining as the project progresses. In contrast, it also shows the “Cost of Changes” starting out low and increasing as the project progresses. What is the key insight a project manager should gain from this graph?
A. Stakeholder influence is not important at the end of the project.
B. Make changes as early in the project as possible.
C. Set aside money for expected changes at the end of the project.
D. Place the project on hold until all changes are made.
3. 很多项目经理曾经见过一张图,该图显示了相关方的影响在开始时高,随着项目的进展降低;相反地变更的成本在开始时低,随着项目的进展升高。项目经理应该从这张图上获得什么样的洞见?
A. 相关方的影响在项目结束时不重要
B. 项目变更应该尽早做出
C. 在项目结束时应该为预期的变更拨付资金
D. 把项目搁置,直到所有的变更都完成。