欢迎大家来到思摩特呼和浩特PMP培训中心,今天总结了我们部分学员的一些易错PMP考试试题给大家分享下。
1. You have overheard two functional managers arguing about the impacts that your project will have on their departments. What is your best response?
A. Do nothing
B. Analyze and report to each manager the impact your project will have on their departments in terms of time and resources required and the relative enterprise priority of your project.
C. Inform the managers that the project sponsors already considered this impact when they decided to implement the project
D. Put in advance requests for resources from each department
1. 你无意中听到两个职能经理在争论你的项目对他们部门的影响。你最好的应对措施是什么?
A. 什么都不做
B. 根据时间和所需资源以及项目在企业的优先级等情况,分析并向每个经理汇报项目对他们部门的影响。
C. 通知经理,当项目发起人决定实施项目时,已经考虑到了这种影响
D. 提前向每个部门申请资源
2. Lucy is managing website development project in an agile environment. She wants to create a burndown chart to present the project’s progress to the stakeholders. She adds a diagonal line representing the ideal burndown and a line for daily actual remaining work. She now needs to show the likely variance at the iteration completion. What should she do?
A. Add a forecast trend line to the ideal burndown line
B. Add a correlation line between the daily actual remaining work and the ideal burndown
C. Add a forecast trend line to the daily actual remaining work
D. Add a median line between the daily actual remaining work and the ideal burndown
2. 露西在敏捷环境中管理网站开发项目。她希望创建一个燃尽图,向相关方展示项目的进展。她添加了一条对角线,代表理想的燃尽和每日实际剩余工作的一条线。现在,她需要在迭代完成时显示可能的差异。她应该做什么?
A. 将预测趋势线添加到理想的燃烧线
B. 在日常实际工作和理想燃烧之间添加一条关联线
C. 将预测趋势线添加到日常实际剩余工作中
D. 在日常实际剩余工作和理想燃烧之间增加中间线
3. Bottom-up Cost estimating is typically motivated by the size and complexity of:
A. The project management software
B. The statistical relationship between historical data and other variables
C. The project budget
D. The inpidual schedule activity or work package
3. 自下而上的成本估算通常是由( )的规模和复杂性引起的:
A.项目管理软件
B.历史数据与其他变量之间的统计关系
C.项目预算
D.个人的进度活动或工作包