欢迎大家来到思摩特杭州PMP考试认证培训,今天总结了我们部分学员的一些易错PMP考试试题给大家分享下。
1. In predictive projects, the scope baseline for the project is used to analyze a project’s scope performance. On the other hand, projects with adaptive lifecycles use:
A. WBS
B. WBS dictionary
C. Scope statement
D. Backlogs
1. 在预测项目中,项目的范围基线用于分析项目的范围性能。另一方面,具有自适应生命周期的项目应使用:
A. WBS
B. WBS字典
C. 范围说明书
D. 未完项
2. Which of the following statements is not accurate about the initial phase of a project?
A. The highest uncertainty is at this stage of the project.
B. The cost associated at the beginning of the project is highest
C. Stakeholders have maximum influence during this phase.
D. Staffing levels are the lowest at this stage.
2. 下列项目的启动阶段陈述中哪项不准确?
A. 最高的不确定性是在项目的这个阶段
B. 项目开始时的相关费用最高
C. 相关方在这一阶段的影响最大
D. 在这一阶段,人员配备水平是最低的
3. Which of the following graphical techniques visually depict the product scope by showing a business system and how other systems interact with it?
A. Ishikawa diagram
B. Histogram
C. Influence diagram
D. Context diagram
3. 下列图形技术中的哪一种是通过描述业务系统和其他系统如何与之交互,来直观地描述产品范围的?
A. 石川图
B. 柱状图
C. 影响图
D. 系统交互图