1.The following table shows the story of an agile project version. If the team completes story a, Story B and 50% in the first iteration How fast is the team?
- A、9
- B、10
- C、12
- D、15
以下表格列出了某个敏捷项目版本的故事。如果团队在第一次迭代中完成故事 A、故事 B 以及 50%的故事 C,那么团队的速度是多少?
- A、9
- B、10
- C、12
- D、15
2.Agile teams are taking longer cycles to develop functions, and increasing cycle time leads to poor quality. What rules should the team adopt to improve quality?
- A. Lean delivery time rule
- B. Law of diminishing returns
- C. Little's law
- D. Parkinson's law
敏捷团队正在花较长的周期来开发功能,增加周期时间导致质量较差。团队应当采用哪项法则改进质量?
- A、精益交付时间法则
- B、收益递减定律
- C、利特尔法则
- D、帕金森定律
3.What should agile management professionals do to maintain a visibility, monitoring and prioritized list of risks and issues?
- A. Conduct team building activities, risk reviews and iteration reviews
- B. Using information sources, daily station meetings and planning meetings
- C. Ensure that the project is fully documented
- D. Ensure that risk and problem logs continue to be maintained
敏捷管理专业人士应该怎么做以维护一份含可见度、监控性并具有优先/顷序的风险和问题清单?
- A、进行团队建设活动、风险评审和迭代回顾
- B、利用信息发射源、每日站会和规划会议
- C、确保项目具有全面的文档
- D、确保继续维持风险和问题日志