1.An efficient agile team should:
- A. Be committed to the success of the team, but respect the roles and titles of team members
- B. Have the decision and commitment of the team and ensure the success of the team at all costs
- C. Self organizing, empowering decision making and consistency driven, constructive confrontation
- D. To produce high business value by strengthening cooperation and avoiding conflict
一个高效的敏捷团队应该:
- A、致力于团队的成功,但要尊重团队成员的角色和头衔
- B、拥有团队的决策和承诺,并不惜一切代价确保团队成功
- C、自组织,授权决策并且一致性驱动,进行建设性对抗
- D、通过强化协作和避免冲突来产出高商业价值
2.In the iteration plan, the team discusses the design of a user story. A team member said that because the future system is complex, a design document is necessary. Another team member responded that in agile, there is no need for documentation. What should SM do?
- A. Agree not to document because it slows the team down
- B. Explaining valuable iterations is higher than documentation, but it doesn't mean documentation is forbidden
- C. Ask the manager if the design needs documentation
- D. Ask Po if spending time on documents will affect manpower
在迭代计划中,团队讨论一个用户故事的设计。一个团队成员说因为未来系统复杂,所以必须要一个设计文档。另外一个队员回应说在敏捷中,不需要文档。SM 应该怎么做?
- A、赞同不要写文档,因为这会让团队进展缓慢
- B、解释有价值的迭代高于文档,但是并不是说文档是被禁止的
- C、请教管理者这个设计是否需要文档化
- D、请教 PO 如果花时间在文档上的话会不会影响人力
3.Which of the following techniques is used by the project team to estimate the amount of work that should be done for each iteration?
- A. Speed measurement
- B. Relative priority
- C. Plan Poker
- D. Version plan
以下哪项技术被项目团队用来估算每个迭代应该完成的工作量?
- A、速度测量
- B、相对优先级
- C、计划扑克
- D、版本计划