1. How is risk monitored and controlled in agile projects?
A. Through team building exercises
B. Through information radiators, daily stand-up meetings, iteration reviews, and iteration retrospectives.
C. Through comprehensive documentation
D. Risk is not monitored and controlled on agile projects
敏捷项目中如何监控和控制风险?
A.通过团队的建立练习
B.通过信息发射源,每日站立会议,迭代审阅和迭代回顾
C.通过全面文档化
D.敏捷项目中不监控和控制风险
2、Which of following helps an agile team promote simple and effective communication?
A. Through the use of lengthy memorandums.
B. Through collaborative release planning
C. Through the use of formal boardroom meetings
D. Through the use of e-mail.
下列哪项能够帮助 AGILE 团队进行简便和有效的沟通?
A.利用冗长的备忘录
B.进行协同发布计划
C.举行正式的董事会会议
D.利用邮件
3、Kyle' s team just completed a sprint. The team had estimated that it could complete 45
story points, but only completed 30 story points in thesprint. How many story points would be a safe estimate for to estimate for the next sprint?
A.45
B.30
C.50
D.40
凯尔的团队刚完成了一个迭代,团队估计可完成 45 个故事点,但是在冲刺里只完成了 30 个,那么多少个故事点会是下一个迭代的安全估算?
A .45
B. 30
C. 50
D. 40