欢迎大家来到思摩特哈尔滨PMP培训中心,今天总结了我们部分学员的一些易错PMP考试试题给大家分享下。
1. Your company is behind schedule in the deployment of a government-mandated change to a health care processing system that must be in production by the end of the year. To meet the due date, you and your team have met and decided to hire an additional 50 programmers to work with the existing staff. This is an example of what?
A. Resource Leveling
B. Fast Tracking
C. Crashing
D. Risk Transference
1. 你的公司已经落后于政府授权的医疗保健处理系统变革项目的进度计划,该项目必须在年底前投产。为了达到预定的日期,你和你的团队会面后决定雇佣另外50名程序员来与现有的员工一起工作。这是什么的例子?
A. 资源平衡
B. 快速跟进
C. 赶工
D. 风险转移
2. Megawatt is estimating the expected cost of a new ERP system deployment project using the actual costs of an earlier similar ERP system deployment project as the basis for the cost. This is what type of estimating?
A. Analogous
B. Bottom-up
C. Expert Judgment
D. Parametric
2. 麦格瓦特正在估算一个新的ERP系统部署项目的预期成本,该项目使用的是早期类似的ERP系统部署项目的实际成本,作为成本的基础。这是什么类型的估算?
A. 类比估算
B. 自下而上
C. 专家判断
D. 参数估算
3. Which of the following statements regarding Resource Leveling and Resource Smoothing is correct:
A. Resource Smoothing can cause the original critical path to change, while Resource Leveling doesn’t alter the project’s critical path
B. Both Resource Leveling and Resource Smoothing can alter the project’s critical path.
C. Neither Resource Leveling nor Resource Smoothing alters the project’s critical path.
D. Resource Leveling can cause the projects’ critical path to change, while Resource Smoothing doesn’t alter the project’s critical path
3. 关于资源平衡和资源平滑的下列陈述有哪些是正确的:
A. 资源平滑会导致原始的关键路径发生改变,而资源平衡不会改变项目的关键路径
B. 资源平衡和资源平滑都可以改变项目的关键路径
C. 资源平衡和资源平滑都不会改变项目的关键路径
D. 资源平衡会导致项目的关键路径发生改变,而资源平滑不会改变项目的关键路径