欢迎大家来到思摩特哈尔滨PMP培训机构,今天总结了我们部分学员的一些易错PMP考试试题给大家分享下
1. The banks in the Ukraine have raised the annual interest rates sharply to 30 percent. You have the option to invest your money either in Ukrainian banks or to build a small factory for a client. The total cost of building the factory will be $12 million but it will spread evenly over one year ($1 million payable by the end of each month for the next 12 months). The client will make a payment of $3.9 million at the end of each quarter from the start of the project. Which of the following is the best option (if you are only considering the return on investment)?
A. Build the factory for the client
B. Invest the money in the bank for a year
C. Both options offer the same payoff
D. Information given is insufficient to determine the best option
1. 乌克兰的银行将年利率大幅提高到30%。你可以选择在乌克兰的银行投资,或者为客户建造一个小工厂。建造工厂的总成本将是1200万美元,但它将在一年内平均分配(在未来12个月中每个月底支付100万美元)。在项目开始的每个季度末,客户将支付390万美元。以下哪一个是最好的选择(如果你只考虑投资回报)?
A. 为客户建造工厂
B. 将钱投资给银行一年
C. 两种选择都提供相同的回报
D. 信息不足无法做出最好的选择
2. Which of the following are short, textual descriptions of required functionality often developed during a requirement gathering workshop:
A. Fishbone diagrams
B. User stories
C. Histograms
D. Decision trees
2. 以下哪一项是经常在收集需求研讨会上制定的所需要的功能的简短和文字性的描述?
A. 鱼骨图
B. 用户故事
C. 直方图
D. 决策树
3. Which of the following is an example of rolling wave planning in a project following an adaptive life cycle?
A. Iterative scheduling with a just-in-time log
B. Predictive scheduling with no backlog
C. Inflexible scheduling without leads and lags
D. Iterative scheduling with a backlog
3. 以下哪一项是一个遵守适应型生命周期项目进行滚动式规划的例子?
A. 带有准时制日志的迭代进度计划
B. 带有未完项的预测进度计划
C. 没有提前量和滞后量的无灵活性的进度计划
D. 带有未完项的迭代进度计划