1、 What types of topics does an agile team cover when it performs reflection?
A. How to stop the customer from changing requirements
B. How to encourage team members to work overtime to maintain project schedule
C. How to reinforce successful practices
D. How to discourage any newly tried successful practice that the team did not agree to
during project chartering
敏捷团队进行回顾过程中通常讨论的话题包括
A.如何劝止客户 改变需求
B.如何激励团队成员加班以保持项目进度
C.如何施行成功的行为
D.如何劝阻任何项目大纲期间团队有异议的新试成功的实践
2、How may variance and trend analysis be incorporated into an agile project?
A. In iteration review meetings
B.In a release plan
C. In formal risk review meetings
D.In a retrospective
变化幅度和趋势分析如何并合入敏捷项目?
A.在迭代评审会议
B.在发布计划
C.在正式风险评审会议
D. 在回顾中
3、James and his agile team are reviewing a chart that shows the risk severity over time of their current project. What information radiator is James looking at?
A.Severity graph
B. Severity burndown graph
C. Risk burndown graph
D.Impact graph
詹姆斯他们的敏捷团队正审阅一份图表,查看他们现时的项目随着时间的风险严重度。詹姆斯在寻找以下哪一信息发射源?
A.严重度图表
B.严重度燃尽图
C.风险燃尽图
D.影响力图