欢迎大家来到思摩特贵阳PMP培训班,今天总结了我们部分学员的一些易错PMP考试试题给大家分享下:
1. What is the primary risk when including reserves, or contingency allowances, in your cost estimate?
A. Cancelling your project
B. Understating the cost estimate
C. Overstating the cost estimate
D. Tracking the funds
在成本估算中,包含应急储备的主要风险是什么?
A. 取消项目
B. 低估项目成本
C. 高估项目成本
D. 追踪资金
2. Which of the following statements most accurately describes a project scenario?
A. Changes in project scope during the initial phases of the project are very expensive.
B. The influence of the stakeholders is the same all through the project.
C. Staffing peaks during the execution phase of a project.
D. The next phase of a project should never start until the deliverables for the previous phase are completely reviewed and approved.
下面哪一项陈述最准确地描述了一个项目场景?
A. 项目初始阶段的项目范围变更是非常昂贵的。
B. 所有项目的利益相关者的影响是相同的。
C. 人员配置在项目执行阶段达到高峰。
D. 直到前一阶段的可交付成果被完全审查和批准,不应该开始项目的下一阶段
3. Which of the following is not an organizational process asset used during the Plan Resource Management process?
A. Template for resource management plan
B. Resource management policies and procedures
C. Historical information about previous projects
D. Standardized stakeholder list
以下哪一项不是规划资源管理过程使用的组织过程资产?
A. 资源管理计划的模板
B. 资源管理的政策和程序
C. 以往项目的历史信息
D. 标准化的相关方清单