1. Robert is managing a road construction project. Due to unseasonal weather conditions, the team productivity might be above or below target. This is an example of:
A. Ambiguity risk
B. Variability risk
C. Mitigated risk
D. Opportunity risk
1. 罗伯特正在管理一个公路建设项目。由于季节性的天气状况,团队的生产力可能高于或低于目标。这属于:
A. 模糊性风险
B. 变异性风险
C. 减轻风险
D. 机会风险
2. The Cost of Quality principle includes:
A. The costs of ensuring conformance to requirements
B. The costs involved when changes are made to the requirements
C. The cost of deploying a project Configuration Management System
D. The costs associated with eliminating requirements
2. 质量成本的原则包括:
A. 确保符合要求的成本
B. 变更时所涉及的费用
C. 部署项目配置管理系统的成本
D. 消除需求相关的成本
3. The business case to justify a project typically contains:
A. The project’s BAC and ETC
B. Identification of alternatives
C. Project WBS
D. Variance Analysis
3. 商业论证证明一个项目的价值,通常包含:
A. 项目的BAC和ETC
B. 备选方案识别
C. 项目WBS
D. 偏差分析