01、What type of baseline includes a combination of scope, schedule and cost?
A. Quality baseline
B. Integrated baseline
C. Overall project baseline
D. Performance measurement baseline
下列哪种基线综合了范围、进度和成本?
A、质量基线
B、综合基线
C、总体项目基线
D、绩效测量基线
02、A project is completed, however, the project was delayed, causing cost overruns at the end of the project.What should the project manager do in this case?
A. Document the circumstances as lessons learned
B. Focus attention on archiving the financial records for this project
C. Evaluate all the work of the project and compare the results to the project scope
D. Document the circumstances surrounding project completion during the scope verification process
项目虽然完成了,但是却延期,导致项目结束时成本超支。在这种情况下,项目经理应该怎么做?
A、将这种情况记录为经验教训
B、将注意力集中在存档该项目的财务记录上
C、评估项目的所有工作,并将结果与项目范围相比较
D、在范围核实过程记录项目完成相关的情况
03、In response to a government requirement,company A initiates a project. The project manager will develop a project charter based on information provided by the project sponsor.Which of the following high-level sections is in the
project charter?
A. Communications plan
B. Procurement plan
C. Summary budget
D. Enterprise environmental factors
为响应一项政府要求,A公司启动了一个项目。项目经理将根据项目发起人提供的信息编制项目章程。下列哪一项属于项目章程中的高层次选择?
A、沟通计划
B、采购计划
C、预算汇总
D、企业环境因素