1.完工成本预测计算不包括:
A. EAC = AC + (BAC - EV)
B. EAC = AC + ETC
C. EAC = BAC / CPI
D. EAC = AC + (BAC/CP1)
2. All the following statements about analogous estimating are true except that it:
A. Supports top-down estimating
B. Is a form of expert judgment
C. Has an accuracy rate of ±10% of actual costs
D. Involves using the cost of a previous, similar project as the basis for estimating the cost of the current project
以下哪句关于类比估算的说明是不正确的?
A. 支持自上而下的估算
B. 是一种专家判断的形式
C. 实际成本的准确率为±10%
D. 在估算当前项目成本时可以参照以前类似项目
3.客户要求变更项目,这会增加项目风险。你应先做下列哪项?
The customer requests a change to the project that would increase the project risk. Which of the following should you do before all the others?
A.在新的成本估算中算进该风险的期望货币值 Include the expected monetary value of the risk in the new cost estimate.
B.和客户谈关于该变更的影响 Talk to the customer about the impact of the change.
C.和团队分析变更的影响 Analyze the impacts of the change with the team.
D.变更风险管理计划 Change the risk management plan.