1. Complex projects usually demand preparation and distribution of periodic project performance reports. The contents of performance reports are usually determined early and documented in the project communications management plan. Which of the following is least likely to be a section on a work performance report?
A. Analysis of project forecasts
B. Current status of risks and issues
C. Stakeholder engagement strategy
D. Reserve burn down charts
1. 复杂的项目通常需要准备和定期分发项目绩效报告。绩效报告的内容通常在项目沟通管理计划的早期和文档中确定。下列哪一项最不可能成为工作绩效报告的一部分?
A. 项目预测分析
B. 风险和问题的现状
C. 相关方参与的策略
D. 储备燃尽图
2. Which of the following Manage Quality techniques examines problems, constraints, and non-value- added activities that occur during project work?
A. Sensitivity Analysis
B. Expected monetary value analysis
C. Earned Value Analysis
D. Process Analysis
2. 以下哪一项属于管理质量技术用来检查项目工作中出现的问题、制约和非增值活动?
A. 敏感性分析
B. 预期的货币价值分析
C. 挣值分析
D. 过程分析
3. A process that states how formal validation and acceptance of the completed project deliverables will be achieved is documented in the:
A. Scope Management plan
B. Procurement Management plan
C. Risk Management plan
D. Communications Management plan
3. 一个说明如何正式确认和接受已完成的项目可交付成果的过程将被记录在:
A. 范围管理计划
B. 采购管理计划
C. 风险管理计划
D. 沟通管理计划