1.An important new project has been added. The new team has been composed of relevant personnel from various functional departments. What kind of starting group should the project manager go throughTeam?
- A. Create a project charter, define the roles and responsibilities of each member, and publish it to the team
- B. Arrange an ice breaking meeting to let team members know each other
- C. Build a team and discuss the roles and responsibilities of each team member
- D. Organize team building and let members achieve milestones in a small iteration
新增加一个重要的项目,新团队已经由各个职能部门的相关人员组成,项目经理应该通过什么启动团队?
- A、创建项目章程,定义每个成员的角色和职责,并且发布给团队
- B、安排一场类似破冰的会议,让团队成员彼此认识
- C、组建团队并且讨论每个团队成员的角色和职责
- D、组织建团并让成员在一个小迭代中实现里程碑
2.Which is the best way to speed up the project?
- A. Protect developers from disruption
- B. Minimize customer engagement
- C. Shorten iteration length
- D. Increase the size of the project team
哪个是提升项目速度的最好选项?
- A、保护开发人员以免被中断
- B、最小化客户参与
- C、缩短迭代长度
- D、增加项目团队的规模
3.Who is responsible for ensuring that each user story is related to at least one user or character?
- A. Users
- B. Programmer
- C. Clients
- D. Characters
谁负责确保每个用户故事都至少与一个用户或人物有关?
- A、用户
- B、程序员
- C、客户
- D、人物