本文为大家介绍的是佛山PMP培训机构推荐|模拟题,下面是佛山PMP推荐机构密训题的具体内容,供大家参考,更多PMP考试相关资讯可关注思摩特项目管理
↑ PMI授权办学资质(11年~12年)↑最新资质在PMI官方网站或者思摩特百度百科查询(十年PMP等项目管理教学保证)
1、A project manager terminates a contract for the design of a two-part report, because the first part did not meet the criteria in the statement of work. After a new request for proposal is distributed, the selection committee awards a new contract to another designer.During the contract closure process, the project manager should do which of the following?
A.Review the procurement processes
B.Update the project management plan
C.Include the terminated contract in the lessons learned documentation
D.Prepare a completion certificate for the terminated contract
项目经理终止一份包含两部分设计报告的合同,因为第一部分不能满足工作说明书中的标准。在分发新的请求建议书后,选择委员会将新合同授予另外一个设计师。在合同收尾过程中,项目经理应进行下列哪一项?
A.审查采购过程
B.更新项目管理计划
C.将终止合同包含进经验教训文档中
D.为终止的合同准备一份完工证明
2、A key stakeholder asks the project manager to quantify the project risks. Which of the following documents should the project manager use to provide the requested information?
A.Cost management plan and schedule management plan
B.Schedule management plan and human resource management plan
C.Human resource management plan and cost management plan
D.Scope baseline and cost management plan
一名关键相关方要求项目经理量化项目风险。项目经理应使用下列那一份文件来提供所请求的信息?
A.成本管理计划和进度管理计划
B.进度管理计划和人力资源管理计划
C.人力资源管理计划和成本管理计划
D.范围基准和成本管理计划
3、A project manager contracts with a company for a specific statement of work (SOW). However, the company can now no longer fulfill part of the contract's terms and conditions,What should the project manager do next?
A. Initiate achange request
B. Initiate project closure activities
C. Initiate the negotiation procedures outlined in the agree agreement
D. Ask the company to subcontract the parts of the contract's terms and conditions they cannot fulfill.
项目经理因为某个特定工作说明书(SOW)与一家公司签订合同。但是,该公司目前不能履行合同的部分条款和条件。项目经理下一步应该怎么做?
A.提出变更请求
B.启动项目收尾活动
C.启动协议中规定的协商程序
D.要求该公司分包其不能履行的部分合同条款和条件